Project summary

Hamilton’s wastewater network is under pressure. The western network is at capacity, which means during heavy rain, there’s a higher risk of overflows into our environment. 

This project focuses on core infrastructure improvements to: 

  • reduce wet-weather overflows 
  • ensure our existing water network can operate safely and reliably 
  • support residential development in Glenview and Fitzroy 
  • protect the Waikato River and meet obligations under Te Ture Whaimana o Te Awa o Waikato

 

What we're doing

  • Upgrading the Te Anau wastewater pump station. 
  • Installing a new wastewater pipeline (and re-using an existing abandoned water pipe). 
  • Redirecting wastewater flows from the Te Anau and Splitt wastewater pump stations to the Peacocke wastewater transfer station.

Wastewater upgrades map

This project will

  • Improve wastewater network resilience during wet weather and reduce the risk of overflows.

  • Assist in unlocking growth by increasing the capacity of the western wastewater network.

  • Ensure Hamilton’s wastewater system continues to meet environmental obligations.

Where we’re at with progress

  • Stage 1 - Planning

    2025

    Design work and selecting a construction partner.
  • Stage 2 - Underway

    Early 2026

    Construction begins on the Te Anau pump station upgrades, and the new pipeline. 
  • Stage 3 - Completed

    2027 - 2028

    Works expected to be completed.

Subscribe for project updates

Frequently asked questions

Will there be traffic disruptions?

Yes, temporary traffic management will be in place during construction. This may include detours, or reduced access on certain roads. We’ll provide advance notice and signage to help you plan ahead.

Will there be noise, vibration, or dust during construction?

Yes, you may notice noise from machinery and trenching activities. Contractors will follow approved noise management plans to reduce disruption, and work will generally take place during daytime hours. 

Some vibration and dust are expected during trenching and drilling. Environmental and safety management plans will be followed to minimise these impacts. 